Customer remolded. I told them prior to demo to contact AT&T to move the demarcation point.
Contractor move underground line to another wall. Customer asked me to re-install incoming line. I told them this should be done by AT&T, because they are responsible for the line up to their Demarc.
It was not that I didn't want to terminate that gel filled cable, but I felt that this is AT&T responsibility from the street to the building.

I come back a week later after AT&T was done to find this installed on the incoming lines from the street. This isn't normally how I find the demarcation point terminated. We don't get much lightening in California, but I usually see the protected blocks in the MPOE installed for business lines.

I also thought that the electrician may have installed this, except for the fact that the color code was correct.


[Linked Image from filedn.com]

[Linked Image from filedn.com]