I have a golf course that has a 100 pair privately owned line that joins their clubhouse to the maintenance shop. I am using this line to carry stations out into the shop from the KSU as well as joining the alarm system. There is a pedestal that is basically being used just as a junction point about halfway between the two buildings. I have to get rid of this pedestal because they are putting a driveway right through it. I was going to do a burial enclosure and just join the 100pr with those connectors.

Any other ideas?

I also thought about relocating that pedestal to the side of the new driveway and install a new pestestal on the other side with a new piece of 100pr in between.

Atcom VoIP Phones
VoIP Demo

Best VoIP Phones Canada


Visit Atcom to get started with your new business VoIP phone system ASAP
Turn up is quick, painless, and can often be done same day.
Let us show you how to do VoIP right, resulting in crystal clear call quality and easy-to-use features that make everyone happy!
Proudly serving Canada from coast to coast.

#473642 08/27/05 01:01 PM
Joined: Feb 2005
Posts: 1,018
Member
Offline
Member
Joined: Feb 2005
Posts: 1,018
Is the 100 pair in the ped just 2 cables coming in (100 pair each) spliced together or is there other cables or drops working out of it?

------------------

#473643 08/27/05 01:13 PM
Joined: Jul 2005
Posts: 1,184
Member
OP Offline
Member
Joined: Jul 2005
Posts: 1,184
Just two. They built a new clubhouse last year and cut the 100pr. Somebody ran a new piece from the clubhouse and installed that box for a splice point.

#473644 08/27/05 01:29 PM
Joined: Feb 2005
Posts: 12,343
Likes: 3
Member
***
Offline
Member
***
Joined: Feb 2005
Posts: 12,343
Likes: 3
The easiest and cheapest way would be as you suggest, two pedestals with a new run between.

If the distance isn't too great from one building to the existing pedestal location, it may be worth it to move the pedestal and replace the cable from the building to the new location.

-Hal


CALIFORNIA PROPOSITION 65 WARNING: Some comments made by me are known to the State of California to cause irreversible brain damage and serious mental disorders leading to confinement.
#473645 08/27/05 01:38 PM
Joined: May 2002
Posts: 17,722
Likes: 18
Member
****
Offline
Member
****
Joined: May 2002
Posts: 17,722
Likes: 18
If it's not serving any purpose other than a splice point, bury it and use a good buried encapsulent to keep it from getting wet, also bond it through on the sheath.


Retired phone dude
#473646 08/27/05 02:13 PM
Joined: Feb 2005
Posts: 1,018
Member
Offline
Member
Joined: Feb 2005
Posts: 1,018
I agree - splice it and bury it. As long as you do a really good job - bond it good, close it up good. If the splice is going to be under a drive way, you don't want to have problems with it. But you did say it was 100 pair and not much working out of it, right? I had a similar situation but the splice ended up under a really big green power transformer. A year later we had to replace the section and I don't have a clue why. I thought I did a really good job on it.

------------------

#473647 08/28/05 01:49 AM
Joined: Jan 2002
Posts: 2,328
Moderator-Comdial
*****
Offline
Moderator-Comdial
*****
Joined: Jan 2002
Posts: 2,328
There are some engineering factors that must be considered here.
1) What's the cable depth?
2) What's the depth of the new road base?

#473648 08/28/05 03:48 AM
Joined: Jul 2005
Posts: 1,184
Member
OP Offline
Member
Joined: Jul 2005
Posts: 1,184
Yes, 100pr with not much going through it. No need for that pedestal, just a splice.

I was told it was originally put in with a ground slitter, so it won't be very deep on the one side. The side they cut during construction, may be a little deeper due to them replacing that piece, probably with a backhoe.

The road will be just a new gravel access route to the maintenance shop.

#473649 08/28/05 04:14 AM
Joined: Dec 2004
Posts: 5,722
KLD Offline
Member
Offline
Member
Joined: Dec 2004
Posts: 5,722
I have the same situation at the local golf club --- 6 pr. buried drop that went bad because it was buried down the driveway to the maintenance shop. Rock ledges and washouts. Waiting for the customer to decide if they want it replaced.

The two peds will pay for themselves over the buried splice. Down the road you may need to pick up pairs, repair circuits, etc., but if you splice it you'll have a potential failure point (even if done "right"). I have seen 4" concrete-encased, re-bar strengthened PVC duct "floated" out of the ground, damaging a 200 pr. 19 AWG cable due to heavy equipment traffic.

Maybe a conduit under (GIP -- ooops, Galvinized Iron Pipe) under the road just in case? That way, in the future, you could replace the cable without digging up the roadway.

Use the peds. [Linked Image from sundance-communications.com] KLD (former cable repairman / splicer)

[This message has been edited by KLD (edited August 28, 2005).]


Ken
---------
#473650 08/28/05 01:42 PM
Joined: Jan 2005
Posts: 15,378
Likes: 13
Moderator-Vertical, Vodavi, 1A2, Outside Wire
*****
Offline
Moderator-Vertical, Vodavi, 1A2, Outside Wire
*****
Joined: Jan 2005
Posts: 15,378
Likes: 13
My advice is to buy a couple of cheap pedestals (UPC-BD3) with a new section of cable installed between them is the way to go.

Don't spend the money on a Picabond crimper or the modules themselves if you aren't a cable splicer by trade. It's to much money to spend for just one job. Use Scotchloks and use their crimping tool (don't try slip-joint pliers; you can over-crimp them where they actually cut the wire you are trying to splice).

If you plan to be supporting buried plant repairs on a regular basis, consider investing in tooling for modular splicing systems, such as 710 or MS2. Both are very popular but tooling is expensive. For smaller jobs, like yours, you can just stick with Scotchloks, or an equivalent.

Remember that just connecting the individual pairs back together isn't all that's involved. You will need to make sure that you maintain the sheath (aluminum shield) across the splice. It should also be grounded at the pedestal to a ground rod.

We use 3M #4465 (I think this is close to the part number) for sheath bond connections and "bond braid" that is perforated with eylets to connect to the bond bar in the pedestal. Then, just run #6 copper wire from the bond bar to the pedestal's ground rod.

If you are new to outside plant maintenance, stay away from buried splices. Until you are completely familiar with sheath bond clamps, splicing systems, etc., just keep everything "above ground" in pedestals so that even if you don't do it correctly, it can always be corrected without a shovel.

------------------
Ed
---------
How come there's always enough time to go back and fix it a second time?


Ed Vaughn, MBSWWYPBX
#473651 08/29/05 02:38 AM
Joined: Dec 2004
Posts: 4,096
Member
*
Offline
Member
*
Joined: Dec 2004
Posts: 4,096
All this great info and nobody asked if the can was "bells"

Again this is all great advise but if bell gets there panties in a wad and that can belongs to them look out.

Did the owner have a survey done by the power company and bell before desiding to do this work?

#473652 08/29/05 02:41 AM
Joined: Jan 2005
Posts: 15,378
Likes: 13
Moderator-Vertical, Vodavi, 1A2, Outside Wire
*****
Offline
Moderator-Vertical, Vodavi, 1A2, Outside Wire
*****
Joined: Jan 2005
Posts: 15,378
Likes: 13
No, he said in his original post that it was a privately-owned cable at the site.

------------------
Ed
---------
How come there's always enough time to go back and fix it a second time?


Ed Vaughn, MBSWWYPBX
#473653 08/29/05 03:28 AM
Joined: May 2002
Posts: 17,722
Likes: 18
Member
****
Offline
Member
****
Joined: May 2002
Posts: 17,722
Likes: 18
Well you have several opinions to choose from. I'd still bury it, put a pipe or pvc in if ya want. As long on you use a good encapsulent you shouldn't have any problems, and even if you do you've said you have plenty of spare pairs. Those golf carts and other vehicles using that drive are just going to use the peds for bumper cars.


Retired phone dude
#473654 08/29/05 05:45 AM
Joined: Feb 2005
Posts: 1,018
Member
Offline
Member
Joined: Feb 2005
Posts: 1,018
I've got this cat, you see and I need some advice on how to get the hide off of it. I've gotton some good advice but I'm not sure which way I want to go yet. Any thoughts?

------------------

#473655 08/29/05 07:45 AM
Joined: Dec 2004
Posts: 4,096
Member
*
Offline
Member
*
Joined: Dec 2004
Posts: 4,096
My bad I over looked that little piece of info .
I guess because I could not understand why the can in the middle of the run

Sorry

#473656 08/29/05 08:19 AM
Joined: May 2002
Posts: 17,722
Likes: 18
Member
****
Offline
Member
****
Joined: May 2002
Posts: 17,722
Likes: 18
Right Mark. Think you're going to find this catagory isn't as cut and dried as some of the others. You said it. There's more than one way to skin a cat.


Retired phone dude
#473657 08/29/05 01:31 PM
Joined: Feb 2005
Posts: 1,018
Member
Offline
Member
Joined: Feb 2005
Posts: 1,018
Well I figured out how to get the hide off but my wife says she liked it better the way it was.

------------------

#473658 08/29/05 02:01 PM
Joined: Jul 2005
Posts: 1,184
Member
OP Offline
Member
Joined: Jul 2005
Posts: 1,184
Ok, did a site visit today, shovel in hand. The 100pr is only about 6 inches below and they told me they are going to remove the topsoil and fill it with gravel. I will have to get that piece in the ground deeper. I think the way to go is with 2 peds and a new piece between them dug deeper.

I checked the grounding like you advised me ev and the oringinal cable from the can to the shop has aluminum sheath, but is not grounded. The cable they replaced from the clubhouse to the can has no ground sheath of any sort. I even checked both ends and cut it back a bit in the clubhouse to look at it better. It is burial cable, but no ground shield.

I also noticed they have no protection on either end of this cable as it enters the buildings.

I told them I would do the work (I am not an outside tech of any sort but they have been a great customer). I did say I wanted to do it right this time and had to include some protection on both ends.

#473659 08/29/05 02:45 PM
Joined: Jan 2005
Posts: 15,378
Likes: 13
Moderator-Vertical, Vodavi, 1A2, Outside Wire
*****
Offline
Moderator-Vertical, Vodavi, 1A2, Outside Wire
*****
Joined: Jan 2005
Posts: 15,378
Likes: 13
Well, you are in Bell Canada territory and I suspect that with minimal lightning exposure, it's possible that unshielded cable was permitted at some time. That doesn't make much sense to me though, I mean the shielding isn't just for lightning protection issues. I think it's now an international standard. Not to mention that Bell Canada was once a part of the Bell System with over a hundred years of uniform standards.

I have seen some European cable catalogs that actually sell direct-burial and aerial cable that does not include any form of shielded jacketing and it's not just drop wire. I am not quite sure what that's all about. Here in the United States, the only black cable (aerial or underground, except for drop wire) that I have seen without shielding is IMSA (traffic signal) cable. It resembles telephone cable in every other aspect except for shielding.

As for the lack of protected entrance terminals, I think you know the answer there. Sounds like this job stinks of an unprofessional installation from the get-go. Probably something "the maintance man" did years ago. Sure, we would all love to go in and tell the customer that it's 100% wrong, but they will never believe you. Even if they do, it won't be until it fails and costs them LOTS of money in a lawsuit before they are willing to do anything.

If I were you, I would advise the customer of how it should be done, document what you have told them, then just place two new pedestals with the replacement section of cable buried at a proper depth (I don't know if Canada follows the same regulations we do here due to frost lines, etc.). Channell Commercial Corp. makes some nice rounded, low-profile all-PVC pedestals that might make the risk of golf cart damage less of a concern.

------------------
Ed
---------
How come there's always enough time to go back and fix it a second time?

[This message has been edited by ev607797 (edited August 29, 2005).]


Ed Vaughn, MBSWWYPBX
#473660 08/29/05 03:02 PM
Joined: Dec 2004
Posts: 5,722
KLD Offline
Member
Offline
Member
Joined: Dec 2004
Posts: 5,722
Hey, Mark, "Here, Kitty, Kitty, Kitty".

That cat can be skinned ---- just hope it has been declawed and doesn't have a white stripe down it's back !! [Linked Image from sundance-communications.com]


Ken
---------
#473661 08/29/05 03:33 PM
Joined: Jul 2005
Posts: 1,184
Member
OP Offline
Member
Joined: Jul 2005
Posts: 1,184
Thanks ev.

#473662 08/29/05 04:05 PM
Joined: Feb 2005
Posts: 1,018
Member
Offline
Member
Joined: Feb 2005
Posts: 1,018
It might not be a bad idea to go back to the equipment end and see what kind of termination job and protection is there. Heaven forbid you go to the trouble of doing this just to have some act-of-God knock them out and you get the blame. Heck, we've been blamed for HVAC systems going out a day or two after we did a simple install.

------------------

#473663 08/30/05 03:21 AM
Joined: Jan 2005
Posts: 15,378
Likes: 13
Moderator-Vertical, Vodavi, 1A2, Outside Wire
*****
Offline
Moderator-Vertical, Vodavi, 1A2, Outside Wire
*****
Joined: Jan 2005
Posts: 15,378
Likes: 13
Mark3906:

You are not kidding. Just our truck in the parking lot and everything that stops working from that day forward had something to do with us. It kills me when we are working in a high-rise and a completely different office starts having problems with their paging or something like that. "It must have something to do with what your people were doing ten floors above".

------------------
Ed
---------
How come there's always enough time to go back and fix it a second time?


Ed Vaughn, MBSWWYPBX
#473664 08/31/05 06:10 PM
Joined: Jun 2005
Posts: 261
Member
Offline
Member
Joined: Jun 2005
Posts: 261
I would probably go with one pedestal, and make the other side a splice in a cristy box.
That gives you a test point, and access to both ends of the cable section.
Either that, or just two splices in cristy boxes.

#473665 09/12/05 06:09 AM
Joined: Sep 2005
Posts: 18
Member
Offline
Member
Joined: Sep 2005
Posts: 18
I'm new to the forum, but not new to telephone work. Everyone has given you the possible options, which all are a possibility. For what it's worth, if it were me, I avoid buried splices if at all possible. Doesn't matter to me if it's air core of filled cable.

No protection? Needs protection, period. (there are particular exceptions about bonding and grounding the cable shield when located within the ground potential rise, GPR, area of power generating or sub station, but that is another entirely differenct subject)

One comment, about the non shielded cable. That's a bad deal, not only for lightning purposes, but one big reason is power influence. I've been doing alot of noise and power mitigation and when we have an open cable shield where we have exposure to power, aerial or buried facilities, there is nothing to throw it 180 degrees out of phase from our cable pairs. For those of you that perform noise mitigation, you know what I mean.

Thanks for letting me jump in, and from what I have read so far on this forum, you all have alot of knowledge.


[This message has been edited by mwann (edited September 12, 2005).]

#473666 09/12/05 07:06 AM
Joined: May 2002
Posts: 17,722
Likes: 18
Member
****
Offline
Member
****
Joined: May 2002
Posts: 17,722
Likes: 18
I agree with your analysis of power induction on non bonded cable. If it were me, in that envionment, with what he has to work with, I'd just replace the cable between the two buildings, no peds, no splice and a sheathed cable and protectors for all the reasons stated.


Retired phone dude
#473667 09/12/05 08:57 AM
Joined: Sep 2005
Posts: 18
Member
Offline
Member
Joined: Sep 2005
Posts: 18
justbill,

If it was me, and that was possible, that's exactly what I'd do too.

Sounds like you know about running power influence problems, so having said that, if he can't make MGN connections it won't even matter....

[This message has been edited by mwann (edited September 12, 2005).]

#473668 09/15/05 12:22 PM
Joined: Jun 2004
Posts: 1,367
Member
*****
Offline
Member
*****
Joined: Jun 2004
Posts: 1,367
Gotta throw in my $0.02.

I think I would try and go with 2 vaults. I don't think I would EVER consider burying a splice! I have seen too many pedastals run over detroying the contents. I would definitely convince them to at least start doing things correctly. dig down at least 3' install at least 2' conduit (small run across the road shouldn't be an issue) and install vaults. all futer adds and repairs will be a breeze and no worry of vehicular damage!
as far as protection goes, you should, but economically I doubt it could be done. (Ground rod in the vault and bond your 50 feet of cable section to it? [Linked Image from sundance-communications.com] )
BTW, Vault is equal to a plastic irrigation box.
Good luck, better hurry before the weather changes.


[Linked Image from i26.servimg.com]
TouchPoint Networks.

Serving the Northwest Since 1991
NEC Shoretel Zultys T3 Tadiran
#473669 02/17/06 01:01 PM
Joined: Feb 2006
Posts: 7
Member
Offline
Member
Joined: Feb 2006
Posts: 7
Just a lowly I&R Tech here guys so I'll apologize in advance if this sounds stupid but I didn't catch any distances here and if the run from the "new" ped location to the shop is close enough wouldn't a couple of bsw's work? doesn't sound like we're talking about alot of copper being used here.

Ha just read the dates on the previous posts...
probobly done by now eh? duh.

#473670 02/28/06 06:09 AM
Joined: Feb 2006
Posts: 1
Member
Offline
Member
Joined: Feb 2006
Posts: 1
There are many avenues for you to take........I would consider burying the spice. However, with technolgy changing and the customers demand growing as well. The existing cable may not carry the new circuits, so it may need to be replaced someday. I would purchase the best buried clousure and place a conduit under the drivway for future. Go ahead and bury the splice just be Damn sure your do a good job closing up the splice.......Good luck!!!

Page 1 of 3 1 2 3

Moderated by  EV607797 

Link Copied to Clipboard
Forum Statistics
Forums84
Topics94,279
Posts638,739
Members49,764
Most Online5,661
May 23rd, 2018
Popular Topics(Views)
211,291 Shoretel
188,177 CTX100 install
187,020 1a2 system
Newest Members
Nadisale, andreww, gohunt, Darrick, telecopippo
49,764 Registered Users
Top Posters(30 Days)
Toner 15
dexman 4
teleco 4
jc2it 4
Who's Online Now
3 members (dexman, Toner, sk), 115 guests, and 99 robots.
Key: Admin, Global Mod, Mod
Contact Us | Sponsored by Atcom: One of the best VoIP Phone Canada Suppliers for your business telephone system!| Terms of Service

Sundance Communications is not affiliated with any of the above manufacturers. Sundance Phone System Forums - VOIP & Cloud Phone Help
©Copyright Sundance Communications 1998-2024
Powered by UBB.threads™ PHP Forum Software 7.7.5