What is the recommended depth for armored fiber with a direct burial jacket both under a driveway with heavy truck traffic and not under a driveway?


Bob

With all the variables involved, I am amazed when any voice and data technology works like it is supposed to.
Atcom VoIP Phones
VoIP Demo

Best VoIP Phones Canada


Visit Atcom to get started with your new business VoIP phone system ASAP
Turn up is quick, painless, and can often be done same day.
Let us show you how to do VoIP right, resulting in crystal clear call quality and easy-to-use features that make everyone happy!
Proudly serving Canada from coast to coast.

Joined: May 2007
Posts: 5,058
Likes: 5
Moderator-1A2, Cabling
*****
Offline
Moderator-1A2, Cabling
*****
Joined: May 2007
Posts: 5,058
Likes: 5
I would certainly put it in below the frost line - whatever that is in your area.

I've had to repair quite a bit of fiber that was cut by backhoes, saws, etc. Deeper is better, warning tape laid in the trench above the cable is recommended and rigid pipe is best.

Sam


"Where are we going and why are we in this hand basket?"
Joined: Dec 2008
Posts: 510
Member
OP Offline
Member
Joined: Dec 2008
Posts: 510
Thanks Sam, Is pipe necessary with the direct burial jacket? Frost is at least 4 feet in Minnesota. One recommendation I have gotten is 1 foot below frost. That seems very deep.


Bob

With all the variables involved, I am amazed when any voice and data technology works like it is supposed to.
Joined: Feb 2006
Posts: 150
Member
Offline
Member
Joined: Feb 2006
Posts: 150
We've always gone about a foot below the frost line and no, you don't need to put it in pipe.

Joined: May 2007
Posts: 5,058
Likes: 5
Moderator-1A2, Cabling
*****
Offline
Moderator-1A2, Cabling
*****
Joined: May 2007
Posts: 5,058
Likes: 5
1' below frost is about right. You don't need pipe and if it's a private driveway you're probably OK, but if it's public and the possibility of other contractors exist, I would recommend it.

Just based on past experience. I made a lot of money fixing cut fiber. Nothing like having to patch a 768 strand cable - NOW!

Certainly, just sign here..... :-)

Sam


"Where are we going and why are we in this hand basket?"
Joined: Aug 2008
Posts: 423
Member
Offline
Member
Joined: Aug 2008
Posts: 423
For crossing a driveway have you thought of vertical inlayed fiber?

The city I live in (pop 750,000) is using this now instead of conventional trenched fiber for its city fiber backbone.

Its basically placed in a saw cut just a few inches below the pavement surface.

Here is a link to what the company that won the tender installed in the saw cut. https://www.teraspan.com/vif.php

Joined: Dec 2008
Posts: 510
Member
OP Offline
Member
Joined: Dec 2008
Posts: 510
Thanks, The company that needs the fiber will do the trenching. I have shared my concerns and your suggestions about protecting the fiber, An engineer from General Cable also sent information. We discussed installng pipe under the private driveway.


Bob

With all the variables involved, I am amazed when any voice and data technology works like it is supposed to.
Joined: Aug 2011
Posts: 191
Member
Offline
Member
Joined: Aug 2011
Posts: 191
I think the standard is 3 feet deep and if you stick to the standard when your digging it back up you know to start looking at about 2.5 feet deep. If everybody sticks to the standard then everybody knows communication cable is 3 feet deep.So when your hammering in fence posts 2 feet deep and hit a fiber optic cable then you know someone didn't stick to the standard of burring telecommincation cable 3 feet deep.

Joined: Dec 2008
Posts: 510
Member
OP Offline
Member
Joined: Dec 2008
Posts: 510
Thanks to all for the information. Customer is a asphalt manufacturer and installation company. They had all the equipment to do the digging and install the direct burial fiber. I passed on to them recommendations for depth. We did the fiber terminations and connections to their network. We have done other fiber installations for them in the past, but they have always had buried conduit ready for us.


Bob

With all the variables involved, I am amazed when any voice and data technology works like it is supposed to.
Joined: Jan 2004
Posts: 6,648
RIP Moderator-Nisuko-Tie, General
*****
Offline
RIP Moderator-Nisuko-Tie, General
*****
Joined: Jan 2004
Posts: 6,648
Quote
So when your hammering in fence posts 2 feet deep and hit a fiber optic cable then you know someone didn't stick to the standard of burring telecommincation cable 3 feet deep.
or you call before you dig and have everything marked and place your posts accordignly


Skip
------------------------------------

Serving SW and West central Fl since 1984
Page 1 of 2 1 2

Moderated by  Silversam 

Link Copied to Clipboard
Forum Statistics
Forums84
Topics94,262
Posts638,697
Members49,757
Most Online5,661
May 23rd, 2018
Popular Topics(Views)
211,098 Shoretel
187,712 CTX100 install
186,796 1a2 system
Newest Members
BPopilek, Rich F, LewisR, TDKs79, Buttinset
49,757 Registered Users
Top Posters(30 Days)
dexman 18
Toner 11
TDKs79 8
teleco 4
Who's Online Now
2 members (hitechcomm, nortelvoip), 164 guests, and 240 robots.
Key: Admin, Global Mod, Mod
Contact Us | Sponsored by Atcom: One of the best VoIP Phone Canada Suppliers for your business telephone system!| Terms of Service

Sundance Communications is not affiliated with any of the above manufacturers. Sundance Phone System Forums - VOIP & Cloud Phone Help
©Copyright Sundance Communications 1998-2024
Powered by UBB.threads™ PHP Forum Software 7.7.5