I am trying to find info on local code for Richmond VA about what the requirement is for pulling cable in a Hospital EVEN if it is not plenum ceiling!

Any one have any info???

Atcom VoIP Phones
VoIP Demo

Best VoIP Phones Canada


Visit Atcom to get started with your new business VoIP phone system ASAP
Turn up is quick, painless, and can often be done same day.
Let us show you how to do VoIP right, resulting in crystal clear call quality and easy-to-use features that make everyone happy!
Proudly serving Canada from coast to coast.

Joined: Jan 2005
Posts: 15,378
Likes: 13
Moderator-Vertical, Vodavi, 1A2, Outside Wire
*****
Offline
Moderator-Vertical, Vodavi, 1A2, Outside Wire
*****
Joined: Jan 2005
Posts: 15,378
Likes: 13
Richmond has some very strange requirements and yes, I've been forced to use plenum cable even in non-plenum environments. I think that a big part of the problem is that the chief electrical inspector there used to be the city's fire marshal. They are very strict and there isn't much getting around them.


Ed Vaughn, MBSWWYPBX
Joined: Jul 2007
Posts: 388
Member
Offline
Member
Joined: Jul 2007
Posts: 388
I'd make the call to see what they require. Here despite what the elec inspector says most of the work has to be inspected by the fire dept and yeah they often require things above and beyond the NEC. I have taken to just using plenum in anything commercial.

Joined: May 2007
Posts: 5,058
Likes: 5
Moderator-1A2, Cabling
*****
Offline
Moderator-1A2, Cabling
*****
Joined: May 2007
Posts: 5,058
Likes: 5
We had a similar situation in NYC with the WTC. The AHJ there was the Port Authority; they required all communication cable to be in pipe (end-to-end) AND to be plenum.

Whatever the AHJ wants.

Sam


"Where are we going and why are we in this hand basket?"
Joined: Jun 2001
Posts: 10,949
Moderator-Avaya
*****
Offline
Moderator-Avaya
*****
Joined: Jun 2001
Posts: 10,949
Quote
Originally posted by Silversam:
We had a similar situation in NYC with the WTC. The AHJ there was the Port Authority; they required all communication cable to be in pipe (end-to-end) AND to be plenum.

Whatever the AHJ wants.

Sam
The University of Kentucky campus is the same way Sam.


Avaya SMB Authorized Business Partner. ACIS/APSS
ESI Certified Reseller/Installer
www.regal-comm.com
Joined: May 2007
Posts: 5,058
Likes: 5
Moderator-1A2, Cabling
*****
Offline
Moderator-1A2, Cabling
*****
Joined: May 2007
Posts: 5,058
Likes: 5
Mike -

Nice to know they're crazy everywhere. But at least their craziness creates more work - and not less - like I see so much of these days.

Sam


"Where are we going and why are we in this hand basket?"
Joined: Jun 2001
Posts: 10,949
Moderator-Avaya
*****
Offline
Moderator-Avaya
*****
Joined: Jun 2001
Posts: 10,949
It was the dangest thing I ever saw.
4inch e.m.t. trunks with 24 x 24 pull boxes every 75ft and could not have more than a 260 degree bend between pull boxes.


Avaya SMB Authorized Business Partner. ACIS/APSS
ESI Certified Reseller/Installer
www.regal-comm.com
Joined: May 2007
Posts: 5,058
Likes: 5
Moderator-1A2, Cabling
*****
Offline
Moderator-1A2, Cabling
*****
Joined: May 2007
Posts: 5,058
Likes: 5
I wish every job was like that - as long as they're willing to pay for it.

Years ago I wired Fordham University. A Nightmare. They wanted every cable concealed. If it couldn't be concealed it had to be in wiremold.

We put in 16,000' of wiremold on the job. Some of the buildings were 150 years old.

A Nightmare.

4" with PBs every 75' sounds like a dream.

Sam


"Where are we going and why are we in this hand basket?"
Joined: Jul 2003
Posts: 6,768
Member
Offline
Member
Joined: Jul 2003
Posts: 6,768
Richmond has some very strange requirements and yes, I've been forced to use plenum cable even in non-plenum environments.

Same here, I have had to do this in Charlottesville Virginia when a Richmond firm was in control of the building!

Joined: Jul 2007
Posts: 388
Member
Offline
Member
Joined: Jul 2007
Posts: 388
Years ago we did a job on a reservation school where everything was piped. It was somewhere near 1500 drops. The building was all precast with no interior class rooms. Classrooms were nothing more than office furniture walls. It was two weeks of running conduit before we even started pulling lines.


Moderated by  Silversam 

Link Copied to Clipboard
Forum Statistics
Forums84
Topics94,262
Posts638,697
Members49,757
Most Online5,661
May 23rd, 2018
Popular Topics(Views)
211,100 Shoretel
187,712 CTX100 install
186,800 1a2 system
Newest Members
BPopilek, Rich F, LewisR, TDKs79, Buttinset
49,757 Registered Users
Top Posters(30 Days)
dexman 18
Toner 11
TDKs79 8
teleco 4
Who's Online Now
0 members (), 140 guests, and 24 robots.
Key: Admin, Global Mod, Mod
Contact Us | Sponsored by Atcom: One of the best VoIP Phone Canada Suppliers for your business telephone system!| Terms of Service

Sundance Communications is not affiliated with any of the above manufacturers. Sundance Phone System Forums - VOIP & Cloud Phone Help
©Copyright Sundance Communications 1998-2024
Powered by UBB.threads™ PHP Forum Software 7.7.5